![]() Evaluation is carried out for 35 periods. The project is planned to be completed on Decemwith a duration of 266 days. To control work in the field using CCS and CCP.Įvaluation to find out the time performance applied to the Yogyakarta Lighthouse project. For the calculation of Performance Intensity use PPI, API and CPI. Performance intensity provides information on how quickly an activity can be completed. ![]() Performance Intensity is a calculation carried out to determine the pace of project work. Evaluation is applied using performance intensity methods and Microsoft Project. Project scheduling and consistent evaluation are needed so that the project is completed on time. Time constraints are often a problem in construction projects.